Florida Building Code Practice Exam 2025 - Free Building Code Practice Questions and Study Guide

Question: 1 / 400

If a contractor begins work without a permit, what will the Building Official do?

Assess a fee in addition to the permit fee

When a contractor begins work without obtaining the necessary permit, the Building Official typically assesses a fee in addition to the permit fee. This approach serves as a deterrent against starting projects without proper authorization, as it emphasizes the importance of following the required permitting process. By imposing an additional fee, the Building Official reinforces the regulations set forth in the Florida Building Code and highlights the significance of compliance from the outset of construction activities.

This action helps to ensure that all construction meets safety and building standards, as the permit process is designed to maintain quality and integrity in building practices. The additional fee serves as both a penalty for non-compliance and a means to encourage future adherence to the proper protocols for obtaining permits. This practice allows the work to continue legally while promoting responsibility among contractors regarding compliance with building codes.

Get further explanation with Examzify DeepDiveBeta

Require demolition of the work performed

Cancel the contractor license

Grant an early start permit

Next Question